SYSTEM TYPE |
|
|
|
|
|
|
REQUIREMENT |
|
|
Clean Agent Systems |
Monthly |
Quarterly |
Semi-annual |
Annual |
Other |
Code |
NFPA 2001 |
|
|
System Inspection |
|
|
|
 |
|
4-1.1 |
At
least annually, all systems shall be thoroughly
inspected and tested for proper operation by
competent personnel. Discharge tests are not
required. |
|
|
System Test |
|
|
|
 |
|
4-1.1 |
(Same as above) |
|
|
Weigh Cylinders |
|
|
 |
|
|
4-1.3 |
At
least semiannually, the agent quantity and pressure
of refillable containers shall be checked. |
|
|
Container Test |
|
|
|
|
 |
4-2.1 |
U.S. Department of Transportation (DOT), Canadian
Transport Commission (CTC), or similar design clean
agent containers shall not be recharged without
retesting if more than 5 years have elapsed since
the date of the last test and inspection.
|
|
|
Hose Test |
|
|
|
|
 |
4-3.2.1 |
All
hose shall be tested every 5 years. |
|
|
Room Integrity |
|
|
|
 |
|
4-4 |
At
least every 12 months, the enclosure protected by
the clean agent shall be thoroughly inspected to
determine if penetrations or other changes have
occurred that could adversely affect agent leakage
or change volume of hazard or both. |
|
|
Carbon Dioxide
Systems |
Monthly |
Quarterly |
Semi-annual |
Annual |
Other |
Code |
NFPA 12 |
|
|
System Inspection |
 |
|
|
|
|
1-11.1 |
At
least every 30 days, an inspection shall be
conducted to assess the system’s operational
condition. |
|
|
System Test |
|
|
|
 |
|
1-11.3.2 |
The
following shall be verified by competent personnel
at least annually using available documentation
required in 1-7.2.6. |
|
|
Weigh Cylinders |
|
|
 |
|
|
1-11.3.5 |
At
least semiannually, all high-pressure cylinders
shall be weighed and the date of the last
hydrostatic test noted (see 1-9.5.1) |
|
|
Container Test |
|
|
|
|
 |
1-9.5.1 |
High-pressure cylinders used in fire-extinguishing
systems shall not be recharged without a hydrostatic
test (and remarking) if more than 5 years have
elapsed from the date of the last test. Cylinders
continuously in service without discharging shall be
p |
|
|
Hose Test |
|
|
|
|
 |
1-11.2.1 |
All
system hose including those used as flexible
connectors shall be tested every 5 years in
accordance with 1-11.2. |
|
|
Halon 1301 Systems |
Monthly |
Quarterly |
Semi-annual |
Annual |
Other |
Code |
NFPA 12A |
|
|
System Inspection |
|
|
 |
|
|
4-1.1 |
At
least semiannually, all systems shall be thoroughly
inspected, tested, and documented for proper
operation by trained competent personnel. Tests
shall be in accordance with the appropriate NFPA or
Canadian standards. |
|
|
Container Test |
|
|
|
|
 |
4-2.1 |
DOT, CTC, or similar design Halon 1301 cylinders
shall not be recharged without a retest if more than
five years have elapsed since the date of the last
test and inspection. |
|
|
Hose Inspection |
|
|
|
 |
|
4-3 |
All
system hoses shall be examined annually for damage. |
|
|
Hose Test |
|
|
|
|
 |
4-3.2 |
All
hoses shall be tested every 5 years in accordance
with 4-3.1. |
|
|
Room Integrity |
|
|
 |
|
|
4-4 |
At
least every 6 months the halon-protected enclosure
shall be thoroughly inspected to determine if
penetrations or other changes have occurred that
could adversely affect halon leakage. |